CAPITAL CONSTRUCTION QUARTERLY ACTIVITY



                              Renovate 5 Labs & Offices - Ag. Science North
                                         Project Number: 2122.0
Project Description:                      Scope:   $679,828
The scope of this project includes refurbishing casework, constructing second egress in labs where only one exists, new floor
tilenew ceiling tile, new doors, provide new or refurbished fume hoods as required, upgrade HVAC. Paint, replace ceiling and
floor tile in office suite 222. The $700,000 renovation includes 5 labs and 5 offices which are used by the USDA.

This project has been following the design schedule as proposed and managed by USDA in accordance with the lease
agreement between USDA and UK. CPMD remains design reviewer and construction administration with USDA performing
design coordination tasks.



Consultant: Johnson-McAdams, designers for U. S. Dept. of
Contract # This is an external contract.                           Original Contract Amount:
Total Amendments to Date:                                   Cumulative Amendment Amount:
Describe all amendments:                                          Revised Contract Amount:
N/A


Contractor: Eubank & Steele
Contract# X402906                                                  Original Contract Amount:            $523,900
Total Change Orders to Date: 0                             Cumulative Change Order Amount:
Low Bid:  $523,900                                                Revised Contract Amount:              $523,900
High Bid: $633,950                                               Contract Percent Complete:
Number of Bids:  10
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.

                                       Student Housing Facilities
                                         Project Number: 2153.0
Project Description:                      Scope:   $46,000,000
The University is construction four (4) new residence halls located on two sites at the University of Kentucky, one on the south
campus and one site on the north campus. On the south campus the site is east of the Kirwan Blanding complex, bounded by
Sports Center drive and Complex Boulevard. Three (3), three-story residential halls on the south campus total 534 beds. The
residential hall on the north campus site at the corner of Euclid Avenue and MLK Boulevard will be four-stories with 150 beds.
The total gross square footage is expected to be approximately 220,000 SF, totaling 684 beds, comprised mostly of semi-suite
units.

Consultant: Ayers/Saint/Gross
Contract# A031090                                                  Original Contract Amount:            $545,000
Total Amendments to Date:  1                                Cumulative Amendment Amount:                $187,707
Describe all amendments:                                          Revised Contract Amount:              $732,707
Amendment #1, 3/9/04, an increase of $187,707, was approved for consultant fees to final review documents from
design/builder and provide periodic construction observations. It also covered an increase in reimbursable services
to employ a Geotechnical Consultant during foundation construction.

Contractor: Messer Construction
           * Messer's contract was awarded by RFP process.
Contract# X401834                                                  Original Contract Amount:         $33,775,000
Total Change Orders to Date: 2                             Cumulative Change Order Amount:               $36,691
Low Bid:                                                          Revised Contract Amount:           $33,811,691
High Bid:                                                        Contract Percent Complete:             215300%
Number of Bids:
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.