CAPITAL CONSTRUCTION QUARTERLY ACTIVITY

                    Upgrade Fume Hoods - LC - Life Safety (Research Bldg. #3)
                                    Project Number: 2201.0
Project Description:                 Scope:   $532,000
The scope of work to be performed in this project includes installation of strobic fans, combination eyewash/showers and
securing of hood sashes, installation of sprinklers throughout the building, the replacement of 30" X 60" ceiling tiles, and
enclosing of the 2 stairwells.

Consultant: Biagi, Chance, Cummins, London and Titzer



Contract # A041020K
Total Amendments to Date: 0
Describe all amendments:
No amendments this quarter.



Contractor: Tri State Fire Protection
Contract # X405017
Total Change Orders to Date:
Low Bid:  $170,000
High Bid: $204,800
Number of Bids: 3
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.



      Original Contract Amount:
Cumulative Amendment Amount:
      Revised Contract Amount:



        Original Contract Amount:
Cumulative Change Order Amount:
       Revised Contract Amount:
       Contract Percent Complete:



                          Upgrade Pharmacy Fume Hood I - Life Safety
                                    Project Number: 2135.0
Project Description:                 Scope:   $705,013
The scope of work consists of the following: balance each lab, clean the duct system and reheat coils, replace reheat coil
control valve, pressure independent controls, remove transfer grilles, rework return fan, remove fans on each floor and
install balancing dampers, air handler flow tracking, exhaust fan flow tracking and static pressure control, exhaust fan
frequency drives, makeup air unit controls, makeup air unit frequency drives. The existing supply air handling units and
lab air terminal units will be retained. The laboratories shall be balanced as negative to the return plenum and negative to
other parts of the building. Once the building is properly balanced the airflow dampers are to be manually locked into
position creating a fixed air volume scenario and ensuring a negative pressure condition in the labs. The project scope is
$750,000, with a construction budget of approximately $460,000.

Consultant: Staggs & Fisher



Contract # A041120
Total Amendments to Date:
Describe all amendments:
No amendments this quarter.

Contractor:
Contract # No Construction contracts awarded to date.
Total Change Orders to Date:
Low Bid:
High Bid:
Number of Bids:
Describe all change orders greater than $25,000.00:



      Original Contract Amount:
Cumulative Amendment Amount:
      Revised Contract Amount:



        Original Contract Amount:
Cumulative Change Order Amount:
        Revised Contract Amount:
      Contract Percent Complete:



13



$23,700



$23,700



$170,000



$170,000
    73%



$60,000



$60,000