CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
           CONSTRUCTION CONTRACTS



CONTRACTOR                              PROJECT INFORMATION
Eubank & Steele                           Medical Research Fit-up & Security
Lexington                                      Project Number: 747.3
Contract# U013399-94                                            Contractor Award Amount: $2,158,000
Low Bid: $2,158,000       Total Change Orders: (13) Contractor Cum. Change Order Amount:   $80,095
High Bid: $2,240,000                                    Revised Contractor Contract Amount: $2,238,095
Number of Bids: 5                                                Contract Percent Complete:   100%
Eubank & Steele                           Nursing Building Patio Roof Repair
Lexington                                      Project Number: 1640.0
Contract# U003718-96                                            Contractor Award Amount:      $114,250
Low Bid:   $114,250       Total Change Orders: (1)  Contractor Cum. Change Order Amount:      $602
High Bid:  $127,361                                     Revised Contractor Contract Amount:   $114,852
Number of Bids: 4                                                Contract Percent Complete:   81%
Frank Messer & Sons                               Parking Structure
Cincinnati, OH                                 Project Number: 1530.0
Contract# U003333-95                                            Contractor Award Amount: $7,800,000
Low Bid: $8,088,000       Total Change Orders: (28) Contractor Cum. Change Order Amount:  $465,240
High Bid: $8,397,000                                   Revised Contractor Contract Amount: $8,265,240
Number of Bids: 3                                                Contract Percent Complete:   97%
Notes: The low bid was negotiated down to $7,800,000.
Change Order #2, an increase of $124,685.00 was approved to provide suitable bearing material below slab on
grade. Change Order #4, an increase of $55,999.00 was approved to remove unsuitable rock at caissons. Change
Order #5, an increase of $34,748.00 was approved to modify foundations and fill with lean concrete. Change Order
#6, an increase of $30,464.00 was approved to remove specified foundation slab and to excavate unsuitable soils and
replace with lean concrete. Change Order #8, an increase of $60,000.00 was approved to provide precast and face
brick for pedestrian bridge column. Change Order #17, an increase of $25,600.00 was approved to provide brick
veneer on columns, to separate offices, revise elevator door, and to revise sidewalk at Upper Street entrance.
Change Order #19, a decrease of $65,000.00 was approved to credit the University for Enterprise Zone sales tax
exemption. Change Order #26, an increase of $130,676.00 was approved to construct a pedestrian bridge enclosure,
to provide cold weather additives for concrete within the pedestrian bridge, and to re-orient exit lighting.
M.B. McGregor Co.                           Pediatric Laboratory Renovation
Lexington                                      Project Number: 1644.0
Contract# U003909-96                                            Contractor Award Amount:       $57,900
Low Bid:    $57,900       Total Change Orders: (4)  Contractor Cum. Change Order Amount:    $1,991
High Bid:    $85,618                                   Revised Contractor Contract Amount:     $59,891
Number of Bids: 10                                               Contract Percent Complete:   53%
Kentucky Electric Co.                       Relocate Soccer/Softball Field
Lexington                                      Project Number: 1528.0
Contract# U006834-95                                            Contractor Award Amount:      $150,212
Low Bid:   $150,212       Total Change Orders: (2)  Contractor Cum. Change Order Amount:   $12,486
High Bid:   $243,260                                    Revised Contractor Contract Amount:   $162,698
Number of Bids: 4                                                Contract Percent Complete:   99%



6