CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
Memorial Coliseum Expansion
Project Number;    2196.0
Project Description:                                  Scope:     $30,000,000
This project consists of the addition of men's and women's basketball offices, practice facility, weight training, medical support, locker/shower, facilities ticket office, administrative offices, and minor renovation of existing locker rooms. The estimated total cost of the facility is $30 million, consisting of the $2.5 million for design plus $27.5 million for construction. This project involves the design of a 92,300 square foot Basketball Practice Facility to enhance the University's ability to attract top student athletes. The new facility will alleviate scheduling problems at Memorial Coliseum and will provide amenities in line with other NCAA basketball facilities in the country. The practice facility will be connected to Memorial Coliseum, which is located near the intersection of Lexington Avenue and the Avenue of Champions, and will renovate 7,700 square feet to support volleyball, gymnastics, offices and ticketing.
Consultant: Sherman-Carter-Bamhart/HNTB
Contract #  A041080 Total Amendments to Date:     0 Describe all amendments : No amendments this quarter.
Original Contract Amount:
Cumulative Amendment Amount:
Revised Contract Amount:
$2,000,000
$2,000,000
Contractor: Messer Construction (Construction Manager-At-Risk)
Note:   This is a 'CM-At-Risk' contract. The amount will be increased as sub-contracts are bid and added. *Messer's contract was awarded by RFP process.
Contract #   X502765                                                                              Original Contract Amount:                     $25,221,877
Total Change Orders to Date:      57                                      Cumulative Change Order Amount:                        $434,931
Low Bid:                                                                                                  Revised Contract Amount:                     $25,656,808
High Bid:                                                                                              Contract Percent Complete:                               60%
Number of Bids:
Describe all change orders greater than $25,000.00:
Change Order #27, 03/16/06, was approved for $65,940.07, to adjust contract amount for actual length of drilled piers
over the base length included in the base bid. Change Order #33, 03/31/06, was approved for -$25,240.75 to adjust
contract amount after receiving donation from Harrod Concrete & Stone. Change Order #31, 04/04/2006, was approved
for -$52,052.66, to delete the cost of finish hardware for Aluminum Doors from the Doors, Frames and Hardware
bid as it was already included in another trade contractor's scope of work. Change Order #32, 04/04/2006, was
approved for $293,576.97, to provide a flexible security control system to facilitate frequent changes due to
turnover of student athletes. Revision primarily consists of replacement of conventional mechanical hardware
with stand alone electronic access control hardware.
14