Twenty-Four change orders greater than $25,000 were as follows:
Project 2235.0
Project 2239.0
Project 2239.32
Project 2268.0 Project 2276.1
Construct Biological Pharmaceutical Complex Building
Modify existing structural steel and skin attachments (+) $118,200 Provide for increase in penthouse distribution panel from 600 A to 800 A
(+) $39,323
Provide necessary steel and design coordination for addition of steel required at the window jambs (+) $36,064 Provide revised openings at penthouse roof to accommodate fans (+) $60,874 Construct Patient Care Facility
Modify tower crane foundation due to mud seam (+) $62,263
Increase the size of both main electrical duct banks to correct coordination
between bid pack 5 and bid pack 6 (+) $50,183
Remove bad soil that is unsuitable for the duct bank (+) $25,219
Provide additional excavation for fuel tanks to meet required depth
(+) $32,912
Perform additional excavation due to unsuitable rock (+) $43,493 Perform additional excavation due to unsuitable bearing (+) $30,655 Provide selector switch control for the control valves of the fuel tanks (+) $27,914
Provide a larger drilling rig due to subgrade condition (+) $40,322 Sawcut the CCC tunnel footers and slab for sanitary pipe relocation due to actual existing elevations (+) $27,303
Additional excavation from column line D. 1 to the southeast corner due to found rock (+) $33,766
Provide and install 48 inch diameter sump pit and piping due to discovered groundwater (+) $36,359
Provide two (2) architectural precast panel mock ups (+) $26,723 Provide concrete shear walls at column line 12/E-F and column line 12/L-M (+) $39,922
Provide capability to throttle steam supply to the building (+) $26,540 PCF - Hospital - CUP Expansion
Provide black steel piping in lieu of ductile iron for the boiler water (+) $28,219
Provide access platform in the Northwest corner of the CUP (+) $26,270 Provide for additional costs resulting from late boiler delivery to be back charged to the boiler manufacturer (+) $45,485
Relocate the condensate pump from the BBSRB tunnel to the College of
Pharmacy tunnel to increase versatility of campus system (+) $28,249 Expand Chemistry Physics Building
Provide and install four 6 foot fume hoods and related casework
accommodations (+) $74,833 Upgrade Fume Hoods T.H. Morgan - Life Safety
Provide new conduit, junction boxes and associated voice/data wiring
(+) $29,719
Action taken: Approved      □ Disapproved        □ Other