CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
Renovate Commonwealth Stadium Locker Room
Project Number:    2226.0
Project Description:                                  Scope:     $690,000
This project will serve to expand and renovate the football team's defensive squad locker room to allow both offense and defense to gather in one space. Currently the two squads have separate locker rooms connected by a passageway. Restroom and shower facilities will be relocated. New HVAC systems, exhaust fans, lockers, ceiling treatments and floor coverings are included in this project.
Consultant: James W. Potts Architects
Contract #  A051000II Assn #4 Total Amendments to Date: Describe all amendments : No amendments this quarter.
Contractor: Eubank & Steele Construction
Contract #   X503190
Total Change Orders to Date:     7
Low Bid:      $580,900
High Bid:     $716,207
Number of Bids:    7
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.
Original Contract Amount:
Cumulative Amendment Amount:
Revised Contract Amount:
Original Contract Amount:
Cumulative Change Order Amount:
Revised Contract Amount:
Contract Percent Complete:
$30,000 $30,000
$580,900
$20,791
$601,691
90%
Renovate Football Practice Field - Nutter Training Center
Project Number:    2225.0
Project Description:                                  Scope:     $2,250,000
The project will involve implementation of a feasibility study completed in October of 2003 to renovate the football practice fields directly behind the Nutter Training Center. The existing fields are a "soil-based" natural turf (3 total) and the fourth is an artificial turf field. The project will be issued as a design/build RFP to install two (2) "sand-based" natural turf fields, one (1) synthetic turf field and remove the artificial turf covering on the artificial turf field so that it can be used as a parking lot. Miscellaneous associated work will include relocation of the existing camera/observation tower, new irrigation system for natural turf areas, new lighting for synthetic turf areas and adjacent natural turf areas and miscellanous electrical outlets, goal posts sleeves and timing clocks.
Original Contract Amount:
Cumulative Amendment Amount:
Revised Contract Amount:
Consultant: No Consultant contract awarded.
Contract #
Total Amendments to Date:
Describe all amendments :
Contractor: Sportsfields
*Sportsfields' contract was awarded by RFP process.
Contract #   X502655                                                                              Original Contract Amount:
Total Change Orders to Date:                                                  Cumulative Change Order Amount:
Low Bid:                                                                                                  Revised Contract Amount:
High Bid:                                                                                               Contract Percent Complete:
Number of Bids:
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.
$1,850,937
$1,850,937 54%