CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
Renovate M.I. King Library
Project Number: 2270.00 Project Description: Scope: $2,250,000
Renovate the 2nd and 3rd floors of the M. I. King Library, 1962 Addition, to accommodate the relocation of the Chemistry Library, Physics Library and a computer lab, all currently housed in the Chemistry-Physics Building. The Math Library, currently housed in the lower level of the Patterson Office Tower, will be included as well. The majority of the renovation will occur on the 3rd floor of the M. I. King Library, with a smaller area on the 2nd floor and minor work on the 4th floor. An existing elevator, located inside the south entrance vestibule, is to be replaced with new components within the existing elevator shaft. All staff areas to include hard wired computer outlets and wireless capability to be provided in addition to the hard-wired throughout.
Consultant: Pearson & Peters
Contract* A081090 Total Amendments to Date: Describe all amendments : No amendments this quarter.
Original Contract Amount: Cumulative Amendment Amount: Revised Contract Amount:
$106,700
$106,700
Contractor: Woodford Builders Contract* 4500024256 Total Change Orders to Date: Low Bid: $956,000 High Bid: $1,158,000 Number of Bids: 5
Describe all change orders greater than $25,000.00: No change orders greater than $25,000 this quarter.
Original Contract Amount: Cumulative Change Order Amount: Revised Contract Amount: Contract Percent Complete:
$956,000
$956,000 45%
Renovate Outpatient Clinic in Kentucky Clinic
Project Number: 2283.00 Project Description: Scope: $2,930,000
This project consists of renovating approximately 13,300 square feet of existing space on the first floor of the Kentucky Clinic, which is to be vacated by the University Health Services (Student Health Facility) to create a new outpatient clinic for the Kentucky Neuroscience Institute (Neurology, Neurosurgery and Physical Medicine & Rehabilitation clinical services). This project includes renovation of part of the space and refurbishment of all of the space. After completion of the construction work associated with this renovation, KNI departments will move into this space.
Consultant: JRA Architects Contract #
Total Amendments to Date: Describe all amendments : No amendments this quarter.
Original Contract Amount: Cumulative Amendment Amount: Revised Contract Amount:
$235,686
$235,686
Contractor: No construction contract awarded to date.
Contract #
Total Change Orders to Date: Low Bid: High Bid: Number of Bids:
Describe all change orders greater than $25,000.00:
Original Contract Amount: Cumulative Change Order Amount-Revised Contract Amount: Contract Percent Complete:
14