CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
Upgrade Cancer Center Radiologic Facility - Hospital
Project Number: 2252.00 Project Description: Scope: $6,000,000
The University of Kentucky Hospital needs to significantly upgrade and improve the current clinical space in the Lower Level of University Hospital. This will include therapy rooms, clinic exam areas, infusion space, office, education, and support space for the clinical practice. Given that the clinic will need to continue operations during the project, it is anticipated that areas will be taken down, or phased, during the construction. Surge space to allow the phasing has been identified. The addition will be located along the west side of the Markey Cancer Center/Ben F. Roach Cancer Care Facility, while the renovation will occur in existing research space on the on the Lower Level of the same building. Development of Radiation Medicine clinical areas is essential to growth of cancer programs supportive of the strategic plans for UK HealthCare. Current facilities are split between the Lower Level of the hospital and the Roach Building. Several initial facility studies have been completed that identified expansion and renovation of the areas of the Lower Level of the Roach Building to respond to immediate needs and is consistent with the Ambulatory Master Plan.
Consultant: BSA Lifestructures
Contract* AO71130 Total Amendments to Date: Describe all amendments : No amendments this quarter.
Original Contract Amount: Cumulative Amendment Amount: Revised Contract Amount:
$535,000 $535,000
Contractor: Woodford Builders, Inc.
Contract* 4500024505
Total Change Orders to Date: 2
Low Bid: $4,935,000
High Bid: $5,190,000
Number of Bids: 3
Describe all change orders greater than $25,000.00: No change orders greater than $25,000 this quarter.
Original Contract Amount: Cumulative Change Order Amount: Revised Contract Amount: Contract Percent Complete:
$4,935,000 $2,090 $4,937,090 24%
Upgrade Fume Hoods TH Morgan - Life Safety
Project Number: 2276.00 Project Description: Scope: $2,234,480
To accommodate the needs of contemporary research and biology instruction, this project will update the fume hood exhaust and air supply systems. The project will also provide needed renovations and upgrades of teaching and research labs to accommodate eight new Biology faculty members.
Consultant: Denham-Blythe
Contract* A081100 Total Amendments to Date: Describe all amendments : No amendments this quarter.
Original Contract Amount: Cumulative Amendment Amount: Revised Contract Amount:
$214,800
$214,800
Contractor: Denham Biythe Company
*Price Contract Contract* 4500021969 Total Change Orders to Date: 3 Low Bid: High Bid: Number of Bids:
Describe all change orders greater than $25,000.00: No change orders greater than $25,000 this quarter.
Original Contract Amount: Cumulative Change Order Amount: Revised Contract Amount: Contract Percent Complete:
$1,587,580 $18,073 $1,605,653 84%
16