Upgrade Surgical Services
Project Number: 2231.00 Project Description: Scope: $4,500,000
This project will renovate existing space to develop a Same Day Surgery Intake Unit; will relocate surgical offices adjacent to the operating rooms in the Critical Care Center to expand the Post Anesthesia Care Unit; will develop a Pre-op, PACU, and waiting space in the main hospital building dedicated to pediatric patients; and will renovate the 1st floor surgical waiting area. The current layout and size of unit causes numerous inefficiencies in the department. The amount of PACU beds is too few based on industry standards. This renovation will allow for improved operational efficiencies of the operating rooms and will provide for an improved patient experience with the development of the same day surgery intake unit. This space is connected to the Hospital's central chilled water and steam systems (coal or gas fired boilers/chillers).
Consultant: Stengel Hill Architects
Contract* A061140 Total Amendments to Date: Describe all amendments : No amendments this quarter.
Original Contract Amount: Cumulative Amendment Amount: Revised Contract Amount:
$324,000
$324,000
Contractor: Woodford Builders Contract* 450000004839 Total Change Orders to Date: 32 Low Bid: $3,280,000 High Bid: $4,199,700 Number of Bids: 5
Describe all change orders greater than $25,000.00: No changes orders greater than $25,000 this quarter.
Original Contract Amount Cumulative Change Order Amount Revised Contract Amount Contract Percent Complete
$3,328,150 $17,808 $3,345,958 100%