CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
 
Expand & Upgrade Livestock Disease Diagnostic Lab
Project Number: 2234.00
Project Description: SCOP9 $27.155200 :
New space is needed for more than one veterinaw pathologist to perform animal postmortem examinations in addition to
renovation of current necropsy space. New space is also needed to add molecular biology/special procedures
capabilities to the laboratory. New technology in the form of an alkaline hydrolysis digester is needed to replace an aging
incinerator. The Livestock Disease Diagnostic Lab is an office and laboratory building with net assignable space ot 3,860
square feet for offices and 28,100 square feet of laboratories and support space. lt is proposed to add 6,300 and 1,200
square feet (net) of new laboratory and ofhce space, respectively. An existing necropsy laboratory and support space will
be renovated (2,000 square feet net).
Consultant: CIVIW, Inc.
Contract # A061100 = Original Contract Amount: $648,000
Total Amendments to Date: 4 Cumulative Amendment Amount: $1,849,300
Describe all amendments : Revised Contract Amount: $2,497,300
Amendment # 1, 12/12/06, was approved for $90,000 to provide additional design services to accommodate a phased
implementation consistent with the legislative budget action. Includes the additional design to study the new tissue
digester effluent impact of the LFUCG Town Branch Wastewater Treatment Plant. Amendment # 2, 12/10/07, an
increase of $131 ,000 was approved for additional schematic design services to include multiple methods of animal
carcass disposal including rendering, incineration and digestion. Amendment # 3, 7/16/08, an increase of$1,625,800 to
provide all of the architectural and engineering services required to complete Schematic Design, Design Development,
Construction Documents and Construction Administration phases for an estimated $20,000,000 worth of construction at
the existing UK Livestock Disease Diagnostic Center Facility. Amendment 4, 5/10/11, an increase of $2,500 was ·
approved to prepare site drawings and technical specifications for the purpose of bidding the final top coat of
asphalt construction.
Contractor: Congleton—Hacker Company (Construction Manager—At»Risk)
Note: This is a 'CM—At—Risk’ contract. The amount will be increased as subcontracts are bid and added.
*C0ngleton—Hacker's contract was awarded by RFP process.
Contract # 4500026910 Original Contract Amount; $18,146,148
Total Change Orders to Date: 201 Cumulative Change Order Amount: $1,506,944
Low Bid: Revised Contract Amount: $19,653,092
High Bid: Contract Percent Complete: 98%
Number of Bids:
Describe all change orders greater than $25,000.00:
Change Order # 6, 8/21/09, was approved for an increase of $45,000 to provide dense graded aggregate (DGA) hll
under the buildings concrete slabs. The DGA was incorrectly detailed and is required for correct construction ofthe
building concrete slabs. Change Order # 19, 12/14/09, was approved for an increase of $44,983 to select a better
match to existing bricks than the proposed brick. The General Shale brick that was bid was deemed unacceptable in the
project mock-up wall. Change Order # 35, 12/21/09, was approved for an increase of $64,388 to provide temporary
paving around Necropsy. This portion of the paving was purposefully deferred during bidding due to market fluctuation.
Change Order # 49, 3/1/10, was approved for an increase of $28,360 to add matching freestanding wall on top of
‘ retaining wall to create a min. 42" high wall. This prevents any chance of falling and improves site grading requirements
adjoining the wall. Change Order # 56, 3/17/10, was approved for an increase of $35,91 0 to provide for rental of a trailer
necessary for the temporary relocation of UK College of Ag. pathologists. The pathologists must be temporarily relocated
to allow for existing facility renovation work to proceed. Change Order # 77, 4/21/10, was approved for an increase of
$43,516 to modify wall to provide additional stud cavity to conceal pipes and conduit. This also eliminates sloped cap ,
and makes it flush for cleanability. Change Order # 91, 6/7/10, was approved for an increase of $50,835 to provide mold
resistant gypsum board in dry areas and moisture resistant gypsum board in wet areas. Change Order # 98, 7/20/10,
was approved for an increase of $40,187 to implement changes to address the issue of excessive moisture in the soil
around necropsy. Change Order # 103, 7/27/10, was approved for an increase of $32,794 to install base course of
asphalt in remaining areas on site that were not included in the contract due to construction phasing and timing. Change
Order # 105, 7/28/10, was approved for an increase of $226,148 to provide coatings consistent with UK compliance
standards for animal disinfection. No change orders greater than $25,000 this quarter.
15