CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
 
Renovate 4-H Camps
Project Number: 2310.0
Scope: $2,000,000
Project Description:
The College of Agriculture Cooperative Extension Service and 4-H Youth Development operate 4-H Camping Centers in Nicholas, Pulaski, Laurel
and Hopkins counties. This project will renovate existing cabins by upgrading utility infrastructure, improving finishes, and installing energy
efticient heating and air conditioning systems. The project also will include replacement of existing bunks and mattresses in all the camps.
Additionally, a new cabin will be built that will house 28 campers and 4-l—l staff.
Consultant: Murphy & Graves
Contract # A101000BB Original Contract Amount: $50,000
Total Amendments to Date: Cumulative Amendment Amount;
Describe all Amendments: Revised Contract Amount: $50,000
No amendments this quarter.
Contractor: Churchill ll/lcGee, LLC » Camp Cumberland
Contract # 4500042781
Total Change Orders to Date: 2 Original Contract Amount; $299,000
Low Bid: $299,000 Cumulative Change Order Amount: $49,281
High Bid: $395,000 Revised Contract Amount: $348,281
Number of Bids; 4 Contract % complete: 100%
Describe all change orders greater than $25,000.00: »
Change Order #1, 1/10/11 was approved for an increase of $49,281 to reinforce the structure and bring cabin numbers 9 and 11 up to code
compliance. No change orders greater than $25,000 this quarter.
Contractor: Lewis Brothers, Inc, — Camp Feltner
Contract # 4500042795
Total Change Orders to Date: 2 Original Contract Amount: $174,600
Low Bid: $174,600 Cumulative Change Order Amount: $360
High Bid: $262,000 Revised Contract Amount: $174,960
Number of Bids: 7 Contract % complete: 100%
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.
Contractor: DH Lawson Construction — Camp Redwood
Contract # 4500042805
Total Change Orders to Date: 7 \ Original Contract Amount: $249,937
Low Bid: $249,937 Cumulative Change Order Amount; $178,210
High Bid; $294,000 Revised Contract Amount: $428,147
Number of Bids: 3 Contract % complete: 100%
Describe all change orders greater than $25,000.00:
Change Order # 5, 2/28/11 was approved for an increase of $172,290 to construct cabin numbers 14 and 18. No change orders greater than
$25,000 this quarter. ,
Contractor: Lanham Brothers General Contractors, lnc. — Camp Dawson Springs
Contract # 4500042794
Total Change Orders to Date; 2 Original Contract Amount: $364,285
Low Bid; $364,285 Cumulative Change Order Amount: $503
High Bid: $445,000 Revised Contract Amount: $364,788
Number ot Bids: 3 Contract % complete: 100%
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.
17