CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
 
Upgrade Student Center Infrastructure
Project Number: 2325.00
Project Description: SCOPE? $23·OOO»OOO
The Upgrade Student Center Infrastructure project will repair, upgrade and improve existing building infrastructure
systems that have exceeded their useful life, need to be upgraded to meet current building code requirements, or need to
be upgraded to meet current capacities being exceeded with occupant load, Systems include HVAC, plumbing and
sanitany, mechanical, electrical and lighting, fire suppression/sprinkling, and communications infrastructures As these
infrastructure needs are upgraded, aesthetic and cosmetic upgrades will be made as a result of and in support of
infrastructure upgrades.
; Consultant: Omni Architects
Contract # A1’|113O l Original Contract Amount: $2,028,460
Total Amendments to Datei Cumulative Amendment Amount:
Describe all amendments : Revised Contract Amount: $2,028,460
No amendments this quarter.
Contractor; Nlesser Construction Co. (Construction Manager At-Risk) Note: This is a 'CNI-At—Risk" contract.
The amount will be increased as subcontracts are bid and added. *Il/lesser’s contract was awarded by RFP process.
Contract # 4500047728 Original Contract Amount: $1,034,780
_ Total Change Orders to Date; Cumulative Change Order Amount:
Low Bid: Revised Contract Amount: $1,034,780
High Bid: · : Contract Percent Complete:
Number of Bids;
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.
 
26