CAPITAL CONSTRUCTION QUARTERLY ACTIVITY

                                   Student Housing Facilities
                                   Project Number: 2153.0
Project Description:                 Scope:   $44,170,000
In an effort to respond to issues related to students living off campus, the University has undertaken efforts to assess its
campus housing. Consistent with the recently adopted UK Physical Development Campus Plan 2050 Final Report
December 2002, the University is constructing new dormitories with 684 new beds. The dormitories will be configured
with suites or semi-suite bedrooms and living areas. The dormitories will be located at sites as identified in the Phase 1
Housing-2010 Campus Plan. New housing will include common areas, student activity spaces, academics, food
services, parking and central campus utilities. Completion scheduled for summer 2005.

Consultant: Ayers/Saint/Gross
Contract # A031090                                           Original Contract Amount:            $545,000
Total Amendments to Date:  1                           Cumulative Amendment Amount:               $187,707
Describe all amendments:                                     Revised Contract Amount:             $732,707
Amendment #1, 3/9/04, an increase of $187,707, was approved for consultant fees to final review documents from
design/builder and provide periodic construction observations. It also covered an increase in reimbursable services to
employ a Geotechnical Consultant during foundation construction. No amendments this quarter.

Contractor: Messer Construction
           * Messer's contract was awarded by RFP process.
Contract # X404699                                           Original Contract Amount:         $34,010,823
Total Change Orders to Date: 50                      Cumulative Change Order Amount:              $860,059
Low Bid:                                                     Revised Contract Amount:          $34,870,882
High Bid:                                                  Contract Percent Complete:                 55%
Number of Bids:
Describe all change orders greater than $25,000.00:
Change Order # 8, 05/18/04, was approved for $37,340.37 for 15kV feed from manhole to Copperstown transformer.
Change Order #11, 05/18/04, was approved for $30,018.45 for gas line replacement and relocation. Change Order #15,
06/17/04, was approved for $75,900.00 for construction of structural tunnel and manhole as outlined by Fuller,
Mossbarger, Scott, and May. Change Order #18, 06/29/04, was approved for $48,755.00 for relocation of domestic
water and domestic water pit. Change Order #26, 08/16/04, was approved for $28,246.94 for addition of walls to enclose
the electrical room from the rest of the mechanical room. Change Orders #28 & #29, 08/18/04, were approved for
finishes in all public areas - $223,000.00 for addition of wood flooring and $64,800.00 for carpet. Change Order #31,
08/30/04, was approved for $102,452.00 for hardware changes to install 16 new automated door openers.
Change Order #37, 10119/04, was approved for -$30,312.32 as a window credit for changes requested by UK.
Change Order #46,12101104, was approved for -$86,594.00 for a landscape changeldeduct. The landscaping will
be coordinated by the UK Grounds department.



1 1