CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
 
PCF - Hospital - CUP Expansion
Project Number: 2239.32
Project Description: SC0P€¥ $l3·15O»OO0
This is a portion of the larger Patient Care Facility Project (2239.0). The project includes an 18,000 square foot addition to
the existing Central Utilities Plant on Press Avenue, The expansion will include provisions for two new 125,000 Ib./hr
boilers and additional chillers. The structure will include an enlarged cold well and basement in the cooling section. The
boilers and supporting equipment will be installed underthis project. Chiller purchases are not contemplated at this time.
Consultant: GBBN Inc.
See project 2239.0
Contract # Original Contract Amount:
Total Amendments to Date: Cumulative Amendment Amount:
Describe all amendments : Revised Contract Amount:
Contractor: Messer Construction Co.
Contract # 4500008954 Original Contract Amount: $9,474,000
Total Change Orders to Date: 46 Cumulative Change Order Amount: $783,937
Low Bid: $9,474,000 Revised Contract Amount: $10,257,937
High Bid: $10,400,000 Contract Percent Complete: 99%
Number of Bids: 2
Describe all change orders greater than $25,000.00:
Change Order # 4, 12/10/07, was approved for $37,518 to provide required additional rock and soil drilling. Change
Order # 7, 2/21/08, was approved for an increase of $53,981 to provide temporary building heat until the new dearator
and surge tank are installed. Change Order # 14, 7/23/08, was approved for an increase of $28,219 to change the boiler
water piping from ductile iron to schedule 80 black steel pipe. Change Order # 17, 7/10/08, was approved for an
increase of $26,270 to install new platform in the northwest corner of the CUP addition to provide greater accessibility
and safer access to valves and equipment. Change Order # 21, 7/23/08, was approved for an increase of $45,585 to
provide for additional costs resulting from the late delivery of the boilers provided by the University and resulting
complications which impacted items on the critical path. Liquidated damages collected from the boiler manufacturer will
be applied to the compensation associated with this change order. Change Order # 30, 8/11/08, was approved for an
increase of $28,249 to relocate the new condensate pump from the BBSRB tunnel to the College of Pharmacy tunnel.
Provide valving to allow the pump to pump in either direction. This change allows for more versatile operation of the
campus steam system. Change Order # 34, 10/30/08, was approved for an increase of $52,257 to provide and install
pipe insulation for the new boiler feed water piping and the boiler blow-down piping Change Order # 35, 11/3/08, was
approved for an increase of $34,693 to provide and install two wye strainers and to install and connect the stack gas
analyzers and Horiba panels. Because the boilers were a direct purchase by the University this scope of work was not
originally included in the contract documents. Change Order # 37, 2/2/O9 was approved for $26,661 to revise the Civil
Site plan to provide greater security and improve the utilization of the grounds north ofthe new construction. Change
Order # 44, 2/24/10, was approved for an increase of $25,745 to perform various items of work related to the boiler
installation not included in the contractors original contract documents. Change Order # 45, 2/24/10, was approved for
an increase of $54,881 to install a new VFD for each of eight ventilation fans. The high efficiency boiler operation
required increased building temperature control to manage the combustion process of the burners of the two boilers. No
change orders greater than $25,000 this quarter.
, 14