CAPITAL CONSTRUCTION QUARTERLY ACTIVITY
Repair, Upgrade and Improve CivilISite Infr. (Repair Pedestrian Bridge at Cooper
Project Number: 2318.00
Project Description: Swper $1,055.700
Repair structural elements of the Cooper Pedestrian Bridge. Replace the precast exterior with glass to allow inspection of
the structural steel.
Consultant: BFMJ
Contract # A11107O Original Contract Amount: $76,800
Total Amendments to Date: Cumulative Amendment Amount:
Describe all amendments : Revised Contract Amount: $76,800
No amendments this quarter.
Contractor: No construction contract awarded to date.
Contract # Original Contract Amount:
Total Change Orders to Date: Cumulative Change Order Amount:
Low Bid: Revised Contract Amount:
High Bid: Contract Percent Complete:
Number of Bids:
Describe all change orders greater than $25,000.00:
Replace Wildcat Lodge Student Housing (Wildcat Coal Lodge)
Project Number: 2309.00
Project Description: SCOPBZ $8.050,000
This project consists of the design and construction of a new housing facility of approximately 18,000 GSF to replace the
existing Wildcat Lodge. The new facility is to house the UK men's basketball players in addition to other non-athlete
students. The building will include a controlled main entryway, with combination living/bedroom spaces, a common
space, with dining and gaming rooms. In addition, it will have a conference room and public restrooms in all common
areas. The site will be located just east of the Joe Craft Center.
Consultant: JRA Architects `
Contract # A1 O1 090 Original Contract Amount: $554,253
Total Amendments to Date: 1 Cumulative Amendment Amount: $6,239
Describe all amendments : Revised Contract Amount: $560,492
Amendment 1, 5/11/10, an increase ot $6,239.33 was approved to provide phase 2 geotechnical exploration services as
a reimbursable expenditure. No amendments this quarter.
Contractor: Codell Construction Company
Note: This is a 'CNI-At-Risk' contract. The amount will be increased as subcontracts are bid and added.
*CodeIIā€˜s contract was awarded by RFP process.
Contract # 4500038207 Original Contract Amount: $6,497,970
Total Change Orders to Date: 2 Cumulative Change Order Amount: $8,588
Low Bid; Revised Contract Amount: $6,506,558
High Bid: Contract Percent Complete: 1%
Number of Bids:
Describe all change orders greater than $25,000.00:
No change orders greater than $25,000 this quarter.
19