82



    dated December 18, 1945, and FPHA-SP-1481-2 Contract.of
    Bailment for Reimbursement entered Into between the Fay-
    ette County Board of Educr.ation and the United States of
    Amaerica, Federal Public Housing Authority, executed March
    20, 1946.

          IN 'WITNESS WMEREOF, the parties hereto have set their
    hands this the 20th day of .1arch, 1946.


                                   FAYETTE COUNTY BOARD OF EDUCATION

                         (Signed)  By: W. P. Pemberton
                                          nChairman
     Attest:

     (Signed) D. Y, Dunn           UNIVERSITY OF KENTUCKY
         Executive Secretary
                          (Signed) By  H. L. Donovan
                                           Presicent

     Attest:
(Signed)Frank D. Peterson
        Comptroller

                          * * ** * * * ** *

              22. Upon motion duly made, seconded and carried,
                  the contract between Fayette County Board off
                  Education and. the University of Kentucky is
                  approved and ordered executed by the Presi-
                  dent and Comptroller.



     X. Leveling Ground and Capping Sewer Lines at Charlestown, in-
diana,

     The Comptroller explained that, at the time the University se-
cured houses from Charlestown, Indiana, for the purpose of housing
veterans attending school, it was agreed that the ground upon which
the houses were situated would be left level, and that water pipes
and sewer lines would be capped and left in a condition satisfactory
to the project manager.   Ori:-inally it was planned that the Govern-
ment would pay for this cost but since the University has bought out-
right the 200 houses and received quit-claim deed thereto, it becomes
incumbent upon the University to see that this work is done.    The
Comptroller advised that he had assured the Cleveland FPA office that
the work would be done.



The Board discussed the question and took the following action: